I was at Llechwedd yesterday afternoon.
I was already aware that an "electrics" upgrade was planned for the Deep Mine tour. One positive result of the recent flooding is that this upgrade (including fitting LEDs throughout) will be brought forward and be done imminently. So some definite good has come out of this.
The water level is now back down to Floor B floor level (so it can now be on Graham's list as dewatered again lol).
The incline man rider will be tested next (especially all the safety sensors and switches on Floor 😎. Then other safety tests before it can re-open hopefully very soon after Christmas. Having said that, a wedding is going ahead in the latter part of December (by candle light of course, as is usual).
As was said to me yesterday "We will not be beaten by one pump failure and 100mm of rain in 24 hours, you just watch us!".