One would think by now,over 2yrs since the incident,that the prosectutor would know,that the Gleision had`nt been working on and off for a 100yrs,
Yesterdays radio report on the trial,mentioned shotfiring brought with it 650,000 gallons of water into the 2ft 6in seam,the mention of run in the report,unless they were 60-80yds back,on the plane of the lower conveyor,where there was a walkway alongside,you`d not run in 2ft 6in.
Also a snippet on another news report mentioned the manager did`nt believe there was much water there,
Maybe his defence will be he cannot read.
The inspectors report will be interesting reading.